M2 Stage 2 Data Hall
The NEXTDC M2 Stage 2 data hall was a 7-month base build and fit out programme which added an additional 6MW to M2’s 60MW facility. It consisted of two levels, two data halls, and 15 switch rooms.
Off-site prefabrication techniques and the systematic redesign of the structure, from in situ-poured concrete to a precast solution, led to immediate and unimpeded early access for fit out trades. This enabled fit out activities to begin within 81 days of contract award. The conversion of blockwork and conventionally formed structures to precast floors and walls also removed the need for tension piles and prefabricated façade elements to avoid ‘under and over’ issues.
Stage 2 was constructed adjoining to and integrating with Stage 1 while in operation. To ensure the operations of the existing facility was not impacted during construction, elements of the project were redesigned to diminish interface works and work methodologies were adopted to enable clear segregation.
This project was successfully delivered one month ahead of programme in January 2019.